The first ninety days after you sign
Signing the contract feels like the finish line. It is the start of the period in which most of the expensive decisions are made.
After months of negotiation the contract is signed, the first instalment is paid, and everyone relaxes for a moment. Then the yard’s project team starts asking questions, and they don’t stop. How you set up the first three months shapes the next two or three years.
1. Put your own representative in place
The yard has a project manager whose job is to deliver the boat to the contract. You need someone whose only job is your interest: an owner’s representative with real new-build experience. Appoint them before the first design review, not after the first problem.
2. Protect the money
Most new-build contracts are paid in stages tied to milestones. Check that every instalment paid before delivery is covered by a refund guarantee from an acceptable bank, and that each guarantee stays valid until delivery. Confirm who insures the hull during construction and on sea trials, and for how much.
“The cheapest change is the one you make before the yard has ordered the steel.”
3. Freeze the specification on purpose
Every yard works to a specification freeze date. Before it, changes are conversations. After it, they are change orders with a price and a delay attached. Use the first weeks to walk through the general arrangement room by room with the people who will use the boat, including your captain if you already have one.
4. Agree how changes are handled
Write the process down: who may request a change, how it is priced, who signs it off and how its effect on the delivery date is recorded. A simple, shared change log prevents most of the disputes I have seen at delivery.
5. Decide flag, class and crew plan early
Flag state and classification society affect equipment, crew accommodation and certification. Changing them later is possible but costly. The same goes for crew numbers: they drive cabins, mess space, storage and running costs for the life of the boat.
Your first-90-days checklist
- 1Owner’s representative appointed and introduced to the yard.
- 2Refund guarantees checked, with expiry dates in the diary.
- 3Construction and sea-trial insurance confirmed.
- 4Design review schedule and specification freeze date agreed.
- 5Change-order process written down and shared.
- 6Flag, class and crew plan decided.